

TABLE OF CONTENTS
Breaches of Reference Criteria and Action Level
Monitoring Parameters, Frequency and Duration
QA/QC Procedure and Detection Limits
Other Factors Affecting the Monitoring Results
Actions Taken in the Event of Exceedance
Review of Effectiveness of Road Cleaning Frequency
Review of Monitoring Methodology and Reference Criteria
3.
CONCLUSIONS
List of Tables and Graphs
Table 2.1 Road
Surface Runoff from Carriageway Monitoring Equipment
Table 2.2 Locations
of Road Surface Runoff Monitoring
Table 2.3 Detection
Limit for Monitoring Parameters
List of Figures
Figure
1.1 Layout
of Work Site
Figure
2.1 Road
Surface Runoff from Carriageway Monitoring Locations
List of Appendices
Appendix
A Shenzhen
Bay Crossing Vehicular Traffic (July to November 2007)
Appendix
B Procedural
Guide for Bridge Runoff Monitoring
Appendix
C Action
Levels and Event Action Plans
Appendix
F Road
Surface Runoff from Carriageway Monitoring Results and Graphical Presentations
This is the first Review Report for Bridge Surface
Runoff from Carriageway Monitoring prepared by ENSR Asia (HK) Ltd. (ENSR), the
designated Environmental Team (ET), for the operational phase of the Project
¡§Hong Kong-Shenzhen Western Corridor¡¨. Operation of the Project commenced on 1
July 2007. This report presents the results and findings of the bridge runoff
monitoring work during the first monitoring period (September to November
2007).
Monitoring of surface runoff from the carriageway was
required to be carried out on 6 occasions in the first three months and another
6 occasions in months 7 to 9 after the operation of the HK-SWC bridge. The
monitoring of the first monitoring period has been postponed due to the time
required for obtaining relevant permits and licences before working on the
expressway. The monitoring events commenced in September 2007.
There were a total
of 6 monitoring of bridge surface runoff from carriageway carried out in the
reporting period to fulfill the requirement stipulated in the Environmental
Permits (EP-162/2003/B and EP-290/2007) and EM&A Manuals.
Nitrate
concentration in the reference sample taken from the water tanker was found to
be around 1.08 ¡V 1.66 mg/L and was already above the reference criteria of 0.72
mg/L. The water used for surface runoff monitoring was tap water from the Water
Supplies Department (WSD). According to the ¡§Drinking Water Quality for the
Period April 2006 ¡V March 2007¡¨ issued by WSD, the range of nitrate
concentration in the water supply is <2.5 to 9.9 mg/L with an average of 3.6
mg/L. The nitrate concentration of this level, i.e. 1.08 ¡V 1.66 mg/L, is still
within WSD requirements for potable use.
Elevated nitrate
levels were recorded in the 1st and 2nd composite samples on 27 October 2007.
The increments of the 1st and 2nd composite samples over the reference sample
were 1.74 mg/L and 0.93 mg/L respectively, against the reference criterion of
0.72 mg/L. No action level exceedance was triggered.
No exceedance was
recorded in other parameters in the reporting period.
Key
issue to be considered during the operation of the HK-SWC includes:
¡P
Sufficient cleaning of the carriageway to be carried out by
vacuum air sweeper(s) to remove grits and pollutants.
Further to the comments provided by EPD on the
report, further revision of the review report is required to provide
justification on the monitoring results.
1.1
ENSR
1.2
Operation for the Project commenced on 1 July 2007. Commencement of the first
monitoring period for bridge runoff monitoring was postponed to September 2007
due to the time required for obtaining relevant permits and licences before
working on the expressway. This report summarises the results and findings of the bridge
runoff monitoring work during the first monitoring period (September to
November 2007).
1.3
Due to safety concern and limitation on working on the
bridge deck of HK-SWC, an alternative method was approved by EPD. Detailed
information is provided in Section 2 of this report.
1.4
Further to the comments provided by EPD on the
report, further revision of the review report is required to provide
justification on the monitoring results.
1.1
The
1.2
As stipulated in the EP and the
EM&A Manual, the HK-SWC bridge deck is required to be cleaned by vacuum air
sweeper(s) twice a week to remove grits and pollutants. The layout of the
Project site is provided in Figure 1.1.
1.3
It was required by the EP and
EM&A Manual that the carriageway should be cleaned twice a week by vacuum
air sweeper(s) to remove grits and pollutants.
1.4
Since the commencement of
operation of HK-SWC, the cleaning and maintenance work was carried out by the
maintenance contractor.
1.5
During the operation of the
HK-SWC in the reporting period, vacuum air sweeper was used for road cleaning
on the bridge deck and the cleaning events were carried out at least once every
two days along the hard-shoulder and left-lane of both bounds, which was
already higher than the frequency recommended in the EP and the EM&A
Manual.
Gullies along HK-SWC were cleaned and stagnant water inside the gullies was
removed once every 6 months.
2.1
The monitoring is to determine
the characteristics of bridge runoff in particular the first flush from the
HK-SWC bridge during rain-storm events and to review the frequency of road
cleaning.
2.2
The original method on road
surface runoff monitoring involves installation of equipments onto the bridge
deck or the parapets on both sides of the expressway. After reviewing by
relevant government departments, including the Hong Kong Police Force and Fire
Services Department, the installation of equipment was considered causing
disturbance to other road users including the fire services and police vehicles
during emergency operation and considered relatively unsafe for the ET staff working
on the expressway.
2.3
A procedural guide detailing
the methodology of using a water tanker to simulate an artificial rainfall by
spraying water onto the catchment area of the monitoring gully during bridge
closure at night was prepared. The guide was vetted by the IEC and the Engineer
and was reviewed by EPD. The procedural guide is also provided in Appendix B of
this report.
2.4
The proposed criteria, action level and actions
required are included in Appendix C.
2.5
A portable automatic sampler of
non-contact type, equipped with a suction pipe, was used for sampling. The pump
flow rate is adjustable. Table 2.1 summarises the equipment used.
Table
2.1 Road
Surface Runoff from Carriageway Monitoring Equipment
|
Equipment |
Model |
|
Variable Speed Sampler (with pump head) |
Masterflex Model 7571 |
|
Pump Head |
Masterflex Model 7518 |
2.6
Monitoring
should include in total 12 sampling / rainstorm events (12 sets of data) and cover
the dry season period. A total of 6 sets of sampling data should be collected
during the first 3 months after the opening of the HK-SWC bridge. The other 6
sets of sampling data should be collected in month 7 to month 9 after opening
of the HK-SWC Bridge. The minimum interval between two sampling events shall
not be less than 4 days.
2.7
The
commencement of the road surface runoff monitoring programme was postponed to
September 2007 due to time required for obtaining consent and relevant permits
and licenses from relevant government departments for working on the bridge
deck. The first monitoring period of road surface runoff from carriageway was
carried out from 27 September 2007 to 10 November 2007, while the second
monitoring period commenced in January 2008.
2.8
All
samples were cooled to 4¢XC without being frozen and delivered to a HOKLAS
laboratory within 24 hours for analysis for the following pollutants in highway
runoff:
Total Suspended Solids
Total Organic Carbon
Chemical Oxygen Demand
Nitrite and Nitrate
Total Kjeldahl Nitrogen
Total Phosphorus
Copper
Lead
Zinc
2.9
In each
monitoring event, water samples were collected from six different road gullies,
three on each side of the carriageways.
2.10
The exact monitoring locations were recorded in terms
of nearby lighting pole / highways chainage. The exact monitoring locations are
shown in Figure 2.1 and are listed in Table 2.2 below.
Table 2.2 Locations of Road
Surface Runoff Monitoring
|
Date |
Shenzhen bound |
Hong Kong bound |
|
29 September 2007 |
Lighting Pole BD3776 Chainage 4.2 N |
Lighting Pole BD 4568 |
|
Lighting Pole BD3742 Chainage 3.0 N |
Lighting Pole BD3610 Chainage 2.0 S |
|
|
Lighting Pole BD4638 (Under the speed sign) |
Lighting Pole BD3644 Chainage 3.2 S |
|
|
6 October 2007 |
Lighting Pole BD3779 (Under the speed sign) |
Lighting Pole BD4565 |
|
Lighting Pole BD3742 Chainage 3.0N |
Lighting Pole BD3610 Chainage 2.0S |
|
|
Lighting Pole BD4643 |
Lighting Pole BD3655 |
|
|
13 October 2007 |
Lighting Pole BD3767 |
Lighting Pole 4555 |
|
Lighting Pole BD3742 Chainage 3.0N |
Lighting Pole BD3615 (Under the speed sign) |
|
|
Lighting Pole BD4638 (Under the speed sign) |
Lighting Pole BD3640 |
|
|
27 October 2007 |
Lighting Pole BD3748 (Under the speed sign) |
Lighting Pole BD4553 (Under the speed sign) |
|
Lighting Pole BD3720 (Under the instruction sign) |
Lighting Pole BD3615 (Under the speed sign) |
|
|
Lighting Pole BD4642 (Under the instruction sign) |
Lighting Pole BD3638 Chainage 3.0S |
|
|
3 November 2007 |
Lighting Pole BD3756 |
Lighting Pole BD4553 (Under the speed sign) |
|
Lighting Pole BD3720 (Under the instruction sign) |
Lighting Pole BD3615 (Under the speed sign) |
|
|
Lighting Pole BD4642 |
Lighting Pole BD3638 Chainage 3.0S |
|
|
10 November 2007 |
Lighting Pole BD3747 |
Lighting Pole BD4551 |
|
Lighting Pole BD3720 (Under the instruction sign) |
Lighting Pole BD3618 |
|
|
Lighting Pole BD4636 |
Lighting Pole BD3644 (Under the speed sign) |
2.11
A water tanker with sprinklers was deployed to
spray water on the road surface around the catchment area of the monitoring
gully. It simulated an artificial rain and provided a washing effect on the
road surface under rainstorm event.
2.12
At each monitoring location, the water tanker stopped on the left lane
near the monitoring gully and spray water over the catchment area. The water
would wash the whole area and drain into the monitoring gully. The position of
the tanker and spraying angle of the sprinkler were adjusted to achieve the
best washing effect.
2.13
A portable automatic sampler was used for sampling. The suction tube
inlet was placed at the mid level of the sedimentation pond inside the
monitoring gully. The sampling works started once bridge runoff discharge was
observed from the gully to the connected down pipe.
2.14
Each water sample collected was of 1L in volume and 24 individual
samples were collected in each monitoring event. Four composite samples, each
of 6L, were prepared from the 24 individual water samples for laboratory
analysis. The first composite sample was a mix of the first water sample
collected from each monitoring gully. Similar preparation procedure applied to
the remaining three composite samples.
2.15
Upon mixing, the composite samples were filled into suitable containers
(preserved / non-preserved) based on the testing parameters before delivery.
2.16
An additional composite sample was prepared by mixing the samples taken
from the water tanker before and after the monitoring. This sample was
collected to understand the quality of spraying water and for reference
purpose. The concentration of pollutant of the reference sample was subtracted
from the raw monitoring data to derive the increment, which was then compared
against the reference criteria.
2.17
The samples were cooled to
2.18
ALS Technichem Pty. Ltd. followed comprehensive quality
assurance and quality control programmes. For QA/QC procedures, at least one
duplicate sample was analysed for every batch of 20 samples as required by
HOKLAS. The QA/QC results are summarised in Appendix D.
2.19
The detection limits for the monitoring parameters are listed in Table
2.3.
Table 2.3 Detection Limit for
Monitoring Parameters
|
Parameter |
Recommended Method |
Detection Limit (mg/L) |
|
Total suspended solids |
APHA 2540D |
2 |
|
Total organic carbon |
APHA 5310 B |
1 |
|
Chemical oxygen demand |
APHA 5220 C&D |
2 |
|
Nitrate |
APHA 4500-NO3- |
0.01 |
|
Nitrite |
APHA 4500-NO2- |
0.01 |
|
Total Kjeidahl Nitrogen |
ASTM D3590-89B |
0.1 |
|
Total phosphorus |
ASTM D515-88B |
0.1 |
|
Copper |
APHA 3120B |
0.001 |
|
Lead |
APHA 3120B |
0.01 |
|
Zinc |
APHA 3120B |
0.01 |
2.20
There
were six monitorings of road surface runoff from carriageway carried out in the
reporting period. All monitorings were carried out under fine weather
condition. Meteorological Data, including daily total rainfall, were obtained from
the Hong Kong Observatory on-site wind station at Lau Fau Shan. All weather
data extracted from Lau Fau Shan weather station for September, October and
November 2007 are annexed in Appendix E.
2.21
All
monitoring results and graphical presentation are provided in Appendix F.
2.22
The
average flow rate of water spraying by the water tanker was about 4.0 L/s. Collection of each of the 1L sample was
completed within 2 ¡V 3 minutes.
Total Suspended
Solids (TSS)
2.23
TSS is
the key element in measuring the road surface runoff monitoring since a high
TSS level does not only imply high concentration of particles, but also cause
high concentration of other pollutants, including heavy metals, nutrients,
which would be adsorbed onto the surface of the particles.
2.24
The TSS
levels in six monitorings were generally low. The highest concentration of TSS
was 20 mg/L and the lowest concentration was below the detection limit (i.e.
<2 mg/L).
2.25
There was
no TSS exceedance recorded in the first monitoring period.
Nitrate
and Nitrite (NO3-+NO2-)
2.26
Nitrate
and Nitrite are two of the nutrients for aquatic life. Nitrite ion itself is
relatively unstable and is a transition stage ion to nitrate ion, which is a
more stable form. Nitrite, to aquatic life, is more toxic than nitrate.
2.27
In
comparison with the reference criteria, a relatively high
nitrite and nitrate concentration was recorded and it was mainly attributable
to high nitrate content since the nitrite concentration was generally below
0.01 mg/L in all monitoring results. In fact, nitrate concentration in the
reference sample taken from the water tanker was around 1.08 ¡V 1.66 mg/L and
was already above the reference criterion of 0.72 mg/L. The water used for
surface runoff monitoring was tap water from the Water Supplies Department
(WSD). According to the ¡§Drinking Water Quality for the Period April 2006 ¡V
March
2.28
Regarding the elevated nitrate levels recorded
on 27 October 2007, the increments of the two composite samples over the
reference sample ranged from
0.93 ¡V 1.74 mg/L and exceeded the reference criterion of 0.72 mg/L. In general, the measured concentrations of all parameters were similar
for all 4 composite samples.
2.29
According to the observations during the monitoring,
there was no adverse observation / condition, which would contribute to high
level of pollutants, identified on the bridge deck. On the other hand, the
accumulated water inside the gully may increase the pollutant levels in the
first or even the second sample. Currently, water sample was collected at the
mid level of the gully once runoff is observed discharged from the gully to the
downpipe. The existing pollutant inside the gully may also be a factor of
elevating pollutant level.
2.30
From the
results of Deep Bay Water Quality Monitoring by EPD from 2005 ¡V 2006 at
stations DM1 to DM5, the range of the nitrate concentration was 0.08 ¡V 2.00
mg/L. The maximum increment of the nitrate concentration in the reporting
period was 1.74 mg/L; all monitoring results in the reporting period lied
within the normal range of nitrate concentration in the Deep Bay Water. This
indicated that under normal rainfall condition, the nitrate input from the
bridge runoff water would not have an adverse impact on the environment and ecology
in the Deep Bay Water.
2.31
Furthermore, the associated environmental impact
was considered minimal due to the relatively small volume of runoff water as
compared to the whole Deep Bay area and the low concentration of the pollutants
in the runoff water.
2.32
Temperature,
humidity, wind direction and background air quality, are also factors that
would affect the measured concentration of nitrate and nitrite. Different
humidity indicates different amount of water particles / water content in the
atmosphere. Air pollutants, including NOx, tend to affiliate with water
particles and some would dissolve in water. The concentration of NOx in the
Shenzhen Bay area is relatively high and the water content in the air around
HK-SWC is considered to be high due to the close proximity to the water body of
the bridge. Small amount of pollutants from the air might be contributed to the
measured value.
2.33
According
to the air quality monitoring data from Environmental Protection Department,
the hourly concentration of nitrogen oxides (NOx) between the period 1 August
2006 and 31 July 2007 ranged from 5 mg/m3 to 597 mg/m3 with an average of 106.26 mg/m3 at Yuen Long air quality
monitoring station. Hourly concentration of nitrogen oxides (NOx) between the period
1 August 2006 and 31 July 2007 at Tap Mun air quality monitoring stations
ranged from 0 mg/m3 to 171 mg/m3 with an average of 18.28 mg/m3 and at Mong Kok roadside air
quality monitoring station ranged from 61 mg/m3 to 1451 mg/m3 with an average of 337.63 mg/m3 were also provided for reference.
2.34
Besides
the abovementioned exceedances recorded on 27 October 2007, there was no
exceedance recorded in nitrate and nitrite concentration in the reporting
period.
2.35
There was
no action level exceedance triggered in the reporting period since there was no
3 consecutive monitoring in nitrate and nitrite concentration exceeded the
reference criteria.
Total
Kjeldahl Nitrogen (TKN)
2.36
The Total
Kjeldahl Nitrogen is the sum of ammonia, ammonium and total organic nitrogen.
Since organic nitrogen, ammonia and ammonium undergo nitrification to form
nitrite or nitrate, the nitrification process would consume oxygen. High
concentration of TKN would cause depletion in oxygen and thus causes impact to
the aquatic system.
2.37
The TKN concentrations
in all the samples were low. The highest concentration of TKN measured was 1.5
mg/L.
2.38
All TKN
monitoring results complied with the reference criteria.
Total
Phosphorus (TP)
2.39
Phosphorus
is one of the major nutrients for the aquatic life. Since phosphorus is usually
the limiting nutrients in the aquatic system, excess phosphorus input to the
aquatic environment could lead to eutrophication and trigger algal bloom.
2.40
The total
phosphorus concentration of all monitoring samples were below detection limit
(i.e. <0.1 mg/L). There was no exceedance in total phosphorus recorded in
the first monitoring period.
Total
Organic Carbon (TOC)
2.41
The TOC
concentration measures all the carbon content in organic form. The input of the
organic carbon into the water body may be considered as an addition of
nutrients, since the organic carbon could be decomposed and reused in the
aquatic environment.
2.42
The TOC
concentrations in all 6 samples were generally low. There was a slight increase
in the TOC concentration on 27 October 2007, which was still below the
reference criteria, was considered to be affected by the pollutants accumulated
inside the gullies prior to the monitoring event.
2.43
The
highest measured TOC concentration was 24 mg/L. There was no exceedance in TOC
recorded in the first monitoring period.
Chemical
Oxygen Demand (COD)
2.44
Chemical
oxygen demand measures the concentration of oxidizable chemicals, usually used
as a measurement of organic compound in water.
2.45
The
measured COD concentrations in the monitoring samples were generally low. All
measured COD concentration were below the reference criteria except for the 1st
composite sample taken on 27 October 2007.
2.46
The measured COD concentration in the 1st composite
sample taken on 27 October 2007 was over the reference criteria. However, the
increment was still within the reference criterion and it was not considered as
an exceedance.
2.47
There was no exceedance recorded in the first
monitoring period.
Copper
(Cu), Lead (Pb) and Zinc (Zn)
2.48
Copper,
lead and zinc are heavy metals, which are the most commonly found pollutants in
highways runoff. These heavy metals are usually combined / associated with
sediment particles and are considered to have a direct impact to aquatic life
at a high concentration.
2.49
The
concentration of copper and zinc was slightly increased in the samples taken on
27 October 2007. It was considered that the increased amount of copper and zinc
was due to the pollutants accumulated inside the gullies prior to the
monitoring. Copper deposited onto the carriageway could be generated from the
brake pads / other metallic parts of the vehicles, while zinc could be
deposited from tyres of vehicles.
2.50
Lead is
considered to be one of the most toxic / acute pollutants in water. The
concentrations of lead in all monitoring samples were below detection limit
(i.e. <0.01 mg/L). It could be due to the restriction of use of leaded
petrol / fuel in vehicles.
2.51
The
concentration of copper, lead and zinc in all samples were within the reference
criteria.
2.52
The
background water quality, i.e. water in the water tanker, would affect the
measured concentration of the target pollutants. Therefore, a ¡§blank¡¨ composite
sample was taken from the tanker before and after the monitoring events and
would be used as a reference to compare with the measured value in the other
composite samples. Since the water used for the monitoring is from the water
supply from the Water Supplies Department, the concentration of pollutants in
the water is low. Thus, the influence by the background water quality on the
pollution load from bridge runoff water, which ultimately enters the Deep Bay
Water, is considered insignificant.
2.53
A
notification of exceedance was issued for the exceedance in nitrate and nitrite
concentration on 27 October 2007 in the reporting period.
2.54
Since
exceedance in water quality in the reporting period did not trigger the action
level, i.e. no 3 consecutive monitoring with the same parameter exceeded the
reference criteria, no further action was recommended.
2.55
Concerning the effectiveness of
road cleaning frequency, the bridge runoff monitoring data, the cleaning work carried
out by the maintenance Contractor employed by the Client and site observations were
reviewed.
2.56
In the
reporting period, elevation in nitrate and nitrite concentration was recorded
in the monitoring event on 27 October 2007. Other than that, no elevation of
other parameters was recorded.
2.57
It was
recommended in the EP and EM&A manual, the cleaning frequency shall be
twice a week with any consecutive cleaning events not separated by more than
four days. The cleaning frequency of the carriageway of the Project by the
maintenance Contractor was compatible with the cleaning frequency as required
by the EP and EM&A Manual. In the reporting period, the carriageway was
cleaned at least once every two days along the hard-shoulder and left-lane of
both bounds by a suction road sweeper.
2.58
From the
weekly site audits in the reporting period and the site observation during the
monitoring events, no specific adverse condition was observed.
2.59
In view of
the current road cleaning practices and frequency, the elevation in nitrite and
nitrate concentration recorded on 27 October 2007 was unlikely attributed to
inadequate road cleaning. Rather, such elevation was considered in relation to
the existing pollutants inside the gully, relatively high NOx content in the
ambient air in the region and the application of mean or median value of data
obtained from overseas journals in establishing the criteria, which would be
further discussed in Sections 2.58 to 2.62. Thus, the current road cleaning
practices and frequency was considered effective and sufficient.
2.60
After
reviewing the monitoring method stated in the EM&A manual, it is not
guaranteed that sufficient rainfall events would happen within the monitoring
months and due to the safety concern on working on the bridge deck, an
alternative methodology, which includes using a water tanker to simulate an
artificial rainfall, for bridge runoff monitoring was adopted. The procedural
guide for the alternative method was provided in Appendix B.
2.61
The reference criteria set out in the EM&A
manual were proposed using the mean or median value of the data from different
overseas journals. Since the bridge runoff monitoring at HK-SWC was the first
bridge runoff monitoring established in Hong Kong and there was no background
information and data available before the first monitoring period, no review of
the reference criteria was carried out.
2.62
From the results
of Deep Bay Water Quality Monitoring by EPD from 2005 ¡V 2006 at stations DM1 to
DM5, the range of the nitrate concentration was 0.08 ¡V 2.00 mg/L. The maximum
increment of the nitrate concentration in the reporting period was 1.74 mg/L;
all monitoring results in the reporting period lied within the normal range of
nitrate concentration in the Deep Bay Water. This indicated that under normal
rainfall condition, the nitrate input does not have an adverse impact on the
environment and ecology in the Deep Bay Water.
2.63
Furthermore, the associated environmental impact
was considered minimal due to the relatively small volume of runoff water as
compared to the whole Deep Bay area and the low concentration of the pollutants
in the runoff water.
2.64
It was considered inappropriate to use the mean /
median value of the data as the reference criteria since this would implicate
that, under normal circumstances, there would be about 50% of chance that the
monitoring results would exceed the reference criteria. It is considered that a
more reasonable but relatively higher percentile level on the obtained data
would be more appropriate to be used for establishment of the reference
criteria / action & limit levels.
2.65
In current monitoring, nitrate, nitrite and total
kjeldahl nitrogen concentration were used for determining the nutrient levels,
in terms of nitrogen content, in the water. It is recommended that monitoring
of these parameters should continue.
2.66
Since Deep Bay is an area of ecological
importance, particularly to shorebirds, any input of pollutants to the Deep Bay
water should be minimized. The most concerned pollutants would be heavy metals.
The measured concentrations of heavy metals (copper, lead and zinc) were low
and were well below the reference criteria. Impacts from heavy metals in road
runoff water are considered small. Besides heavy metals, input of nutrients,
including organic carbon, nitrogen-containing chemicals and
phosphorus-containing chemicals, would be another concern, since these
nutrients can lead to extensive growth of algae in the Deep Bay. Yet, the
concentrations of these pollutants are low, the impact to the Deep Bay
environmental is considered small.
2.67
The Deep Bay catchment area is about 535 km2,
which is much larger as compared to the surface area of the bridge deck. As the
concentration of pollutants are low and the volume of runoff from the bridge
deck is small (due to the relatively small surface area), the impact to water
quality and ecology was considered insignificant.
2.68
However, a comprehensive review of recent studies
and literature was recommended and raw data from current monitoring should also
be reviewed for determining the new monitoring programme or reference criteria
in any future road surface runoff from carriageway monitoring in Hong Kong.
3.1
Bridge surface runoff from
carriageway monitoring was carried out in September to November 2007. All monitoring
results in the reporting period were checked and reviewed.
3.2
Six road surface runoff
monitoring events were carried out in the reporting period. All monitoring
results complied with the reference criteria except nitrite and nitrate
level on 27 October 2007. The increments of the two samples ranged from 0.93 ¡V
1.74 mg/L against the reference criterion of 0.72mg/L. The impact from the
elevated nitrate and nitrite concentration to the environment was considered
minimal.
3.3
The measured COD level in the 1st composite
sample was over the reference criterion taken on 27 October 2007. However, the
increment was still within the reference criterion and it was not considered to
be an exceedance.
3.4
No action level exceedance was recorded in the
reporting month.
3.5
The
current cleaning frequency and method of the bridge deck was considered
sufficient and effective.