TABLE OF CONTENTS

EXECUTIVE SUMMARY

1.         INTRODUCTION

Background

2.         PROJECT CHARACTERISTICS

Project Organization and Contacts of Key Management

Construction Activities

3.         ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters and Locations

Environmental Quality Performance Limits (Action and Limit Levels)

Environmental Mitigation Measures

4.         MONITORING RESULTS

Air Quality

Noise

Marine Water Quality

Ecology

5.         AUDIT RESULTS

Implementation Status of Environmental Mitigation Measures

Status of Environmental Licensing and Permitting

Advice on Solid and Liquid Waste Management Status

6.         NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS)

Summary of Exceedances

Review of the Reasons for and the Implications of Non-compliance

Summary of Actions Taken

7.         COMPARISON OF EM&A DATA WITH EIA PREDICATION

1-hour TSP and 24-hour TSP Monitoring

Noise Monitoring

Marine Water Quality Monitoring

Ecology

Review of Environmental Monitoring Methodology and EM&A Programme

Environmental Acceptability of the Project

8.         ENVIRONMENTAL COMPLAINTS

9.         NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS

10.        COMMENTS AND CONCLUSIONS

11.        REFERENCES

 


List of Tables

 

Table 4.1           Summary of monitoring conducted in the reporting period

Table 4.3           Summary of marine water quality exceedances

Table 4.4           Density Comparison at inter-tidal mudflat

Table 4.5           Species Richness at inter-tidal mudflat

Table 4.6           Density Comparison at tideline

Table 4.7           Species Richness at tideline

Table 5.1           Actual Waste Generation throughout the Construction Period

 

 

List of Figures

 

Figure 2.1          Project Organization

Figure 2.2          Layout of Work Site

Figure 3.1          Locations of Air Quality Monitoring Stations

Figure 3.2          Locations of Noise Monitoring Stations

Figure 3.3          Locations of Marine Water Quality Monitoring Stations

Figure 3.4          Locations of Inter-tidal Mudflat and Tideline Avifauna Surveys

Figure 3.5          Locations of Relocated Seagrass

 

 

List of Appendices

 

Appendix A        Contact Details of Key Management

Appendix B       Environmental Monitoring Programme

Appendix C       Action and Limit Levels

Appendix D       Graphical Presentation of Air Quality Monitoring Results

Appendix E       Graphical Presentation of Noise Monitoring Results

Appendix F        Post-Project Impact Water Quality Monitoring Results and

Graphical Presentation of Marine Water Quality Monitoring Results (DOSM, SS, TUR, TBT)    

Appendix G       Graphical Presentation of Inter-Tidal Bird Monitoring Results

Appendix H       Summary Implementation Status of Environmental Mitigation Measures

Appendix I         Status of Environmental Licenses and Permits

Appendix J        Complaint Flow Diagram and Complaint Log

Appendix K       Yellow Forms Log