6.1
Site audits were carried out on a
weekly basis to monitor environmental issues on the site to confirm that all
mitigation measures were implemented properly. The summary of site audit in the
reporting period is attached in Appendix D.
6.2
All permits/licences/notifications
obtained as of the reporting period are summarised in Table 6.1
Table 6.1 Summary of Environmental
Notification, Licensing and Permit Status
|
Permit No. |
Valid Period |
Description |
Status |
|
|
From |
To |
|||
|
Environmental
Permit |
||||
|
EP-162/2003/B |
19 Jan. 04 |
- |
1.
Construction and
operation of a 2.
Construction and
operation of a |
Valid |
6.3
The ET
conducted site inspections on 6, 10, 20 and 25 September 2007.
6.4
No specific finding was
identified in the reporting month.
Environmental Mitigation Implementation Schedule
(EMIS)
6.5
According
to the Environmental Permit, the mitigation measures detailed in the permits
are required to be implemented. An updated summary of the EMIS is presented in
Appendix E.
6.6
The Event
and Action Plans for water quality and feeding shorebirds are presented in
Appendix B.
6.7
Appendix F presents the
environmental complaint flow diagram of the Project.
6.8
No complaint, summon or prosecution related to
environmental issues was received or made against the Project in the reporting
period.