
TABLE OF CONTENTS
Environmental Monitoring Works
Environmental Complaints and
Prosecution
Summary of the EM&A Requirements
2. OPERATIONAL NOISE MONITORING
Monitoring Parameters, Frequency and Duration
Monitoring Parameters, Frequency and Duration
Operational Disturbance on Intertidal Bird
Communities
Bridge Lighting Scheme and Bird Collisions
5. SEDIMENTATION RATE MONITORING
Monitoring Parameters, Frequency and Duration
Status of Environmental Licensing and Permitting
Implementation Status of Environmental Mitigation
Measures
Summary of Exceedances of Environmental Quality
Performance Limit
Implementation Status of Environmental Complaint
Handling Procedures
Key Issues for the Coming Month
Environmental Monitoring Programme for the Next Month
8. CONCLUSIONS AND RECOMMENDATIONS
List of Tables and
Graphs
Table
2.1 The Noise
Monitoring Locations
Table 4.1 Summary of the Density, Growth and Health Condition of
the Mangrove Plantation
Table 6.1 Summary of Environmental
Notification, Licensing and Permit Status
List of Figures
Figure 1.1 Project
Organization
Figure 1.2 Layout
of Work Site
Figure 4.1 Location
of Mangrove Plantation
List of Appendices
Appendix A Contact
of Key Environmental Personnel
Appendix B Requirements,
Event and Action Plans for the Ecological Monitoring during Operation Phase
Appendix C Site
Inspection Records
Appendix D Summary
of Environmental Mitigation Implementation Schedule
Appendix E Complaint
Flow Diagram and Complaint Log
Appendix F Environmental
Monitoring Schedules
This is the twenty-second
monthly Environmental Monitoring and Audit (EM&A) report prepared by ENSR
Asia (HK) Ltd. (ENSR), the designated Environmental Team (ET), for the
operational phase of the Project “Hong Kong-Shenzhen Western Corridor”. Operation
of the Project commenced on
Weekly site audits, monitoring of replanted mangrove and bridge lighting scheme and
bird collisions were carried out in the reporting month. Environmental
mitigation measures and environmental complaint handling procedures were also
implemented.
Noise
No operational noise
monitoring was carried out in the reporting month. The last operational noise
monitoring was completed on 23 June 2008.
Water Quality
No road surface
runoff monitoring was carried out in the reporting month. The last road surface
runoff from carriageway monitoring was completed on 1 March 2008.
Ecology
The eighth monitoring of replanted mangrove was
carried out on 22 April 2009. The
health condition of the mangrove plantation was good at all three zones.
The twenty-second monthly bridge lighting scheme
and bird collisions monitoring was conducted on 24 April 2009. No bird
mortality was recorded in this monitoring.
Sedimentation Rate
Monitoring
No sedimentation rate monitoring was carried
out in the reporting month. The last sedimentation rate monitoring was
completed on 17 June 2008.
Environmental Licensing and Permitting
Permits granted to the Project include the
Environmental Permits for the Project (EP-162/2003/B and EP-290/2007).
Environmental Site Audit
Weekly environmental site audits were carried
out in the reporting month. No specific observation was identified.
There was no reporting change in this month.
No complaint related
to environmental issues was made against the Project in the reporting
period.
Key
issues to be considered in the coming month include:
·
Maintain sufficient cleaning works for the carriageway by vacuum air
sweeper(s) to remove grits and pollutants; and
· Implement the Emergency Response Plan for Spillage of Chemicals.
1.1
ENSR
1.2
Operation for the Project commenced on
1.3
The structure of the environmental management team is
shown in Figure 1.1. Contacts of key environmental staff of the Project are
shown in Appendix A.
1.4
A layout plan of the Project is provided in Figure 1.2.
1.5
The EM&A programme requires environmental monitoring
for operational noise, water quality, ecology and sedimentation rate. The
EM&A requirements for each item are described in subsequent sections,
including:
·
Monitoring parameters;
·
Environmental mitigation measures, as recommended in the project EIA
final report;
·
Environmental requirements in the contract documents.
1.6
Site audits findings are described in Section 6.
1.7
Advice on the implementation status of environmental
protection and pollution control/mitigation measures are summarised in Section 6
of the Report.
2.1
Noise monitoring is required to monitor the operational
noise level at the nearby sensitive receivers during peak traffic hour.
2.2
The measured noise level will be compared to the
predicted traffic noise levels in the EIA under full provision of the
mitigation measures.
2.3
The traffic noise level should
be measured twice within the first year of the road opening. Measurements
should be made in terms of the A-weighted L10 over three 30-mins
periods during the peak traffic hour. Other parameters L90 and Leq
would be included for reference purpose.
2.4
Noise monitoring was required to be carried out at NSRs
SWC-AN1 and SWC-AN2. The monitoring locations are summarized in Table 2.1.
Table 2.1 The Noise Monitoring Locations
|
Monitoring Station |
Location |
Monitoring Type |
Description |
|
SWC-AN1 |
Village House at Ngau Hom Shek |
Façade |
G/F |
|
SWC-AN2 |
Village House at Ngau Hom Shek |
Façade |
G/F |
2.5
Operational noise monitoring
was completed on 23 June 2008. No
monitoring was carried out in the reporting month.
3.1
The monitoring is to determine
the characteristics of bridge runoff in particular the first flush from the
HK-SWC bridge during rain-storm events and to review the frequency of road
cleaning.
3.2
The original method on road
surface runoff monitoring involves installation of equipments onto the bridge
deck or the parapets on both sides of the expressway. After reviewing by
relevant government departments, including the Hong Kong Police Force and Fire
Services Department, the installation of equipment was considered causing
disturbance to other road users including the fire services and police vehicles
during emergency operation and considered relatively unsafe for the ET staff working
on the expressway.
3.3
An alternative proposal on the
monitoring method using a water tanker to simulate an artificial rainfall by
spraying water onto the catchment area of the monitoring gully during bridge
closure at night was prepared. The alternative proposal was approved by EPD. A
procedural guide was also prepared. The guide was vetted by the IEC and the
Engineer and was reviewed by EPD.
3.4
Two
periods of monitoring during the first 3 months and after 6 months of the
opening of the
3.5
The commencement
of the road surface runoff monitoring programme was postponed to September 2007
due to the requirement in obtaining consent and relevant permits and licenses
from relevant government departments for working on the bridge deck. The
monitoring of road surface runoff from carriageway was completed on 1 March
2008.
3.6
All
samples were cooled to 4°C without being frozen and delivered to a HOKLAS
laboratory within 24 hours for analysis for the following pollutants in highway
runoff:
Total suspended solids
Total organic carbon
Chemical oxygen demand
Nitrate and nitrite
Total Kjeldahl Nitrogen
Total phosphorus
Copper
Lead
Zinc
3.7 Water samples were collected from six different road gullies, three on each side of the carriageways. The exact monitoring locations were recorded in terms of nearby lighting pole / highways chainage.
3.8
The
monitoring of road surface runoff from carriageway was completed on 1 March
2008. No monitoring was carried out in the reporting month.
4.1
As required under Clause 6.7, 6.9 and 6.10 of the
Environmental Permit EP-162/2003/B, Clause 3.4 of the Environmental Permit
EP-290/2007 and Section 6.3.2 – 6.3.4 of the EM&A Manual, operational
disturbance on intertidal bird communities,
bridge lighting scheme and bird collisions, and replanted mangroves have to be
monitored bi-monthly (for 2 years), monthly (for 3 years) and quarterly (for 2
years) respectively.
4.2
The trigger and action levels
for bird density for the monitoring on intertidal bird communities are provided
in Appendix B.
4.3 Equipment used for monitoring included a 20-60x telescope, 10x42 binoculars, and a hand-held GPS.
4.4
Two monitoring locations were
selected: Ngau Hom Shek (NHS) and Sheung Pak Nai (SPN). The NHS site locates adjacent to the
4.5 There was no monitoring on intertidal bird communities in the reporting month.
4.6 The next monitoring is tentatively scheduled on 23 May 2009.
4.7 A camera and a pair of binoculars were required during the monitoring process.
4.8 The monitoring of bird collisions took place along the Hong Kong-Shenzhen Western Corridor (HK-SWC), which is approximately 5.5 km long and 40 m wide.
4.9
A survey was conducted to
assess the impacts of different lighting schemes on bird mortality as caused by
collision with the bridge and associated structures. In order to monitor the bird’s mortality, a survey
was carried out along the HK-SWC at both sides of the carriageway covering both
the
4.10 The four lighting schemes are listed as follows:
§ Scheme 1 – Monday to Thursday and Sunday, 19.30-22.00. Architectural lighting for the tower.
§ Scheme 2 – Friday, Saturday and general festival, 19.30-22.00. Architectural lighting for the tower and side faces of the deck.
§ Scheme 3 – Special festival and events, 19.30-22.00. Architectural lighting for the tower, stay cables and the side faces of the deck.
§ Scheme 4 – During inclement weather, turn off the architectural lighting.
4.11 The survey was conducted on 24 April 2009 at 7.30pm. Lighting Scheme 2 was being monitored.
4.12 No dead bird was found on the bridge nor floating on water surface during the survey. There was no significant evidence to suggest adverse impacts from the HK-SWC on bird collision.
4.13 A retractable metallic measuring tape, a soft measuring tape (over 4m) and a camera were used to monitor the growth of mangrove seedlings.
4.14
The monitoring of the survival
and growth of the compensatory mangrove plantation took place right below the HK-SWC
on the mudflat near the shore at NHS (Figure 4.1). The total area of the plantation was
4.15 A survey should monitor the density, growth and health condition of the compensatory mangrove plantation that was being established on 9 February 2007, after the clearance for the construction of the SWC.
4.16 The mangrove plantation was being divided equally into three zones, where Zone 1 was the closest to the shore and Zone 3 was the furthest. Within each zone, three quadrats, which were one square meter in size, were being chosen at random. The number of mangrove planting was counted within each quadrat and the heights of three representative individuals were measured. The heights of the tallest and the shortest individual, and the trunk diameter of the most representative individual were also measured. The health condition of the plantings was also assessed in the scale of good, fair and poor.
4.17 The mangrove plantation monitoring was conducted on 22 April 2009 during low tide condition.
4.18 Table 4.1 summarises the conditions of mangrove plantation during the monitoring survey:
Table 4.1 Summary of the Density,
Growth and Health Condition of the Mangrove
|
|
Zone 1 |
Zone 2 |
Zone 3 |
|
Density (Individuals /
sq. m) |
8.00 |
5.00 |
5.00 |
|
Average Height of 3
Representative Individuals (cm) |
92.9 |
78. 8 |
86.4 |
|
Height - Minimum (cm) |
70.7 |
53.3 |
72.3 |
|
Height - Maximum (cm) |
101. 7 |
84. 7 |
98.7 |
|
Estimated Trunk
Diameter (cm) |
1.2 |
1.1 |
1.3 |
|
Average Health (Good /
Fair / Poor) |
Good |
Good |
Good |
4.19 The results show that Zone 1 had higher density than Zone 2 and 3. There was no obvious change in density of plantings since the initial mangrove survey in October 2007 (seven individuals at Zone 1 and six individuals at Zone 2 and Zone 3).
4.20 In average, Zone 1 and 3 supported the tallest individuals of about 93 and 86 cm in height respectively, while Zone 2 supported the shortest individuals of 79 cm in height. Zone 3 had the highest value for estimated truck diameter for mangrove plants, while Zone 2 had the lowest, though the difference is very minor.
4.21
As suggested in the October
2007 report, environmental factors including substrate composition, salinity
and tidal action could affect the growth pattern of mangrove stands.
4.22 In general, the health condition of the mangrove plantation was good across all three zones.
5.1
As required under Clause 6.2 of the Environmental
Permit EP-162/2003/B, monitoring on the sedimentation rate in
5.2
The monitoring work took place every month starting
from the construction phase and up to one year after the project has commenced the
operation. Additional work may be needed subject to the weather condition.
5.3
Monitoring was carried out at 7 monitoring stations as
specified in the approved Sedimentation Rate Monitoring Plan at Tsim Bei Tsui,
Mai Po mudflat and those between HK-SWC and Tsim Bei Tsui. These include two
locations at Tsim Bei Tsui (Stations P1 & P2), three locations at the Mai
Po Mudflat (Stations P3 to P5) and two locations near Sha Kiu Tsuen (Stations
P6 & P7).
5.4
The sedimentation rate monitoring in
6.1
Site audits were carried out on a
weekly basis to monitor environmental issues on the site to confirm that all
mitigation measures were implemented properly. The summary of site audit in the
reporting period is attached in Appendix C.
6.2
All
permits/licences/notifications obtained as of the reporting period are
summarised in Table 6.1
Table 6.1 Summary of Environmental
Notification, Licensing and Permit Status
|
Permit No. |
Valid Period |
Description |
Status |
|
|
From |
To |
|||
|
Environmental
Permit |
||||
|
EP-162/2003/B |
19 Jan. 04 |
- |
1.
Construction and
operation of a 2.
Construction and
operation of a |
Valid |
|
EP-290/2007 |
20 Nov. 07 |
- |
1.
Operation of a 2.0km
dual 3-lane carriageway elevated structure of the |
Valid |
6.3
The ET
conducted site inspections on 3, 8, 17, 23 and 30 April 2009.
6.4
No specific finding was
identified in the reporting month.
Environmental Mitigation Implementation Schedule
(EMIS)
6.5
According
to the Environmental Permit (EP-162/2003/B), the mitigation
measures detailed in the permits are required to be implemented. An updated
summary of the EMIS is presented in Appendix D.
6.6
No exceedance was recorded in the reporting
month.
6.7
The Event
and Action Plans for feeding shorebirds are presented in Appendix B.
6.8
Appendix E presents the
environmental complaint flow diagram of the Project.
6.9 No complaint, summon or prosecution related to environmental issues was received or made against the Project in the reporting period.
7.1
Key issues to be considered in the coming month
include:
·
Maintain sufficient cleaning works for the carriageway by vacuum air
sweeper(s) to remove grits and pollutants; and
·
Implementation of the Emergency Response Plan for Spillage of Chemicals.
7.2
Tentative environmental monitoring and audit schedule
for the next reporting month is shown in Appendix F.
8.1
Environmental impact monitoring was performed between 1
and 30 April 2009. All monitoring results in the reporting period were checked
and reviewed.
8.2
No operational noise monitoring was carried out in the
reporting month since the monitoring had been completed.
8.3
No road surface runoff from
carriageway monitoring was carried out in the reporting month since the
monitoring had been completed.
8.4
No bird mortality was recorded during this month’s bridge
lighting scheme and bird collisions survey.
8.5
During the monitoring of the
replanted mangrove, the health condition of the mangrove plantation was good at
all three zones.
8.6
No sedimentation rate monitoring
was carried out in the reporting month since the monitoring had been completed.
8.7
No specific observation was
identified during the site audits in the reporting month.
8.8
No complaint, notification of
summons or prosecution related to environmental issues was made against the
Project in the reporting period.
8.9
According to the environmental audits performed, the
following recommendations were made:
·
Maintain sufficient cleaning works for the carriageway by vacuum air
sweeper(s) to remove grits and pollutants.
·
Implement the Emergency Response Plan for Spillage of Chemicals.