

TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY............................................................................................................................... I
Environmental
Monitoring Works I
Reporting
Change I
Environmental
Complaints and Prosecution I
Future Key
Issues I
1. INTRODUCTION.............................................................................................................................. 1
Background 1
Project
Organization 1
Summary of
the EM&A Requirements 1
2. OPERATIONAL NOISE MONITORING............................................................................................... 2
Monitoring
Requirements 2
Monitoring
Parameters, Frequency and Duration 2
Monitoring
Locations 2
Results and
Observations 2
3. WATER QUALITY........................................................................................................................... 3
Monitoring
Requirements 3
Monitoring
Parameters, Frequency and Duration 3
Monitoring
Locations 3
Results and
Observations 3
4. ECOLOGY..................................................................................................................................... 4
Monitoring
Requirements 4
Operational
Disturbance on Intertidal Bird Communities 4
Bridge
Lighting Scheme and Bird Collisions 9
Replanted
Mangroves 9
5. SEDIMENTATION RATE MONITORING............................................................................................ 10
Monitoring
Requirements 10
Monitoring
Parameters, Frequency and Duration 10
Monitoring
Locations 10
Results and
Observations 10
6. ENVIRONMENTAL AUDIT.............................................................................................................. 10
Site
Environmental Audit 10
Status
of Environmental Licensing and Permitting 10
Implementation
Status of Environmental Mitigation Measures 11
Summary
of Exceedances of Environmental Quality Performance Limit 11
Implementation
Status of Environmental Complaint Handling Procedures 11
7. FUTURE KEY ISSUES.................................................................................................................. 11
Key Issues
for the Coming Month 11
Environmental
Monitoring Programme for the Next Month 11
8. CONCLUSIONS AND RECOMMENDATIONS................................................................................... 12
Conclusion 12
Recommendations 12
Environmental
Monitoring Works
Environmental
Complaints and Prosecution
Summary
of the EM&A Requirements
2. OPERATIONAL NOISE MONITORING
Monitoring
Parameters, Frequency and Duration
Monitoring
Parameters, Frequency and Duration
Operational
Disturbance on Intertidal Bird Communities
Bridge
Lighting Scheme and Bird Collisions
5. SEDIMENTATION RATE MONITORING
Monitoring
Parameters, Frequency and Duration
Status of Environmental Licensing and Permitting
Implementation Status of Environmental Mitigation Measures
Summary of Exceedances of Environmental Quality
Performance Limit
Implementation Status of Environmental Complaint Handling
Procedures
Key
Issues for the Coming Month
Environmental
Monitoring Programme for the Next Month
8. CONCLUSIONS
AND RECOMMENDATIONS
List
of Tables and Graphs
Table 2.1 The Noise Monitoring Locations.................................................................................... 2
Graph 4.1 Abundance and Species
Composition of Shorebirds on the Exposed Mudflats (100 m x 100 m Quadrat) at
Ngau Hom Shek and Sheung Pak Nai – 21 May 2009.................................................... 5
Table 4.1 Density and Number of
Shorebird Species Recorded during the Previous EIA and the Survey on 21 May
2009 on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and
Sheung Pak Nai 6
Graph 4.2 Abundance and Species
Composition of Shorebirds along the Tidelines (500 m x 10 m transect) at Ngau
Hom Shek and Sheung Pak Nai – 21 May 2009............................................................. 6
Table 4.2 Density and Number of
Shorebird Species Recorded during the Previous EIA and the Survey on 21 May
2009 along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung
Pak Nai 7
Graph 4.3 Abundance and Species
Composition of Shorebirds on the Strips of Mudflats (250 m x 40 m) “Under
Bridge” and “On Exposed Mudflat” at Ngau Hom Shek – 21 May 2009......................................... 8
Table 6.1 Summary of Environmental Notification, Licensing
and Permit Status............................. 10
Table 2.1 The
Noise Monitoring Locations
Graph 4.1 Abundance and Species
Composition of Shorebirds on the Exposed Mudflats (100 m x 100 m Quadrat) at
Ngau Hom Shek and Sheung Pak Nai – 21 May 2009
Table 4.1 Density and Number of
Shorebird Species Recorded during the Previous EIA and the Survey on 21 May
2009 on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and
Sheung Pak Nai
Graph 4.2 Abundance and Species
Composition of Shorebirds along the Tidelines (500 m x 10 m transect) at Ngau
Hom Shek and Sheung Pak Nai – 21 May 2009
Table 4.2 Density and Number of
Shorebird Species Recorded during the Previous EIA and the Survey on 21 May
2009 along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung
Pak Nai
Graph 4.3 Abundance and Species
Composition of Shorebirds on the Strips of Mudflats (250 m x 40 m) “Under
Bridge” and “On Exposed Mudflat” at Ngau Hom Shek – 21 May 2009
Table 6.1 Summary of Environmental Notification, Licensing
and Permit Status
List
of Figures
Figure
1.1 Project Organization
Figure
1.2 Layout of Work Site
Figure
4.1 Locations of the Monitoring Sites for
Intertidal Bird Communities
List
of Appendices
Appendix
A Contact of Key
Environmental Personnel
Appendix B Requirements, Event and Action Plans for the Ecological
Monitoring during Operation Phase
Appendix
C Site Inspection Records
Appendix
D Summary of Environmental Mitigation Implementation Schedule
Appendix
E Complaint Flow Diagram and Complaint Log
Appendix
F Environmental Monitoring Schedules
This
is the twenty-third monthly Environmental Monitoring and Audit (EM&A)
report prepared by ENSR Asia (HK) Ltd. (ENSR), which was integrated
into AECOM Asia Company Limited as of 1 May 2009, the
designated Environmental Team (ET), for the operational phase of the Project
“Hong Kong-Shenzhen Western Corridor”. Operation of the Project commenced on
Weekly site audits, monitoring
of intertidal
bird communities and bridge lighting scheme and bird collisions were carried
out in the reporting month. Environmental mitigation measures and environmental
complaint handling procedures were also implemented.
Noise
No operational
noise monitoring was carried out in the reporting month. The last operational
noise monitoring was completed on 23 June 2008.
Water Quality
No
road surface runoff monitoring was carried out in the reporting month. The last
road surface runoff from carriageway monitoring was completed on 1 March 2008.
Ecology
The twelfth monitoring of
operational disturbance on intertidal bird communities was carried out on 21
May 2009. During the survey, the physical existence of
the HK-SWC and its shade did not show an adverse impact on the shorebird
communities at NHS.
The twenty-third monthly bridge
lighting scheme and bird collisions monitoring was conducted on 26 May 2009. No
bird mortality was recorded in this monitoring.
Sedimentation
Rate Monitoring
No sedimentation rate
monitoring was carried out in the reporting month. The last sedimentation rate
monitoring was completed on 17 June 2008.
Environmental Licensing and
Permitting
Permits granted to the Project
include the Environmental Permits for the Project (EP-162/2003/B and
EP-290/2007).
Environmental Site Audit
Weekly environmental site audits
were carried out in the reporting month. No specific observation was
identified.
There was no reporting change in
this month.
No complaint
related to environmental issues was made against the Project in the reporting
period.
Key issues to be considered in the coming month include:
·
Maintain sufficient cleaning works for the carriageway by
vacuum air sweeper(s) to remove grits and pollutants; and
· Implement the Emergency Response Plan for Spillage of Chemicals.
1.1
ENSR
1.2
Operation for the Project commenced on
1.3
The structure of the environmental
management team is shown in Figure 1.1. Contacts of key environmental staff of
the Project are shown in Appendix A.
1.4
A layout plan of the Project is
provided in Figure 1.2.
1.5
The EM&A programme requires
environmental monitoring for operational noise, water quality, ecology and
sedimentation rate. The EM&A requirements for each item are described in
subsequent sections, including:
·
Monitoring parameters;
·
Environmental mitigation measures, as recommended in the
project EIA final report;
·
Environmental requirements in the contract documents.
1.6
Site audits findings are described in
Section 6.
1.7
Advice on the implementation status of
environmental protection and pollution control/mitigation measures are
summarised in Section 6 of the Report.
2.1
Noise monitoring is required to monitor
the operational noise level at the nearby sensitive receivers during peak
traffic hour.
2.2
The measured noise level will be compared
to the predicted traffic noise levels in the EIA under full provision of the
mitigation measures.
2.3
The traffic
noise level should be measured twice within the first year of the road opening.
Measurements should be made in terms of the A-weighted L10 over
three 30-mins periods during the peak traffic hour. Other parameters L90
and Leq would be included for reference purpose.
2.4
Noise monitoring was required to be carried
out at NSRs SWC-AN1 and SWC-AN2. The monitoring locations are summarized in
Table 2.1.
Table 2.1 The Noise Monitoring Locations
|
Monitoring Station |
Location |
Monitoring Type |
Description |
|
SWC-AN1 |
Village House
at Ngau Hom Shek |
Façade |
G/F |
|
SWC-AN2 |
Village House
at Ngau Hom Shek |
Façade |
G/F |
2.5
Operational
noise monitoring was completed on 23 June 2008. No monitoring was carried out in the reporting month.
3.1
The monitoring is
to determine the characteristics of bridge runoff in particular the first flush
from the HK-SWC bridge during rain-storm events and to review the frequency of
road cleaning.
3.2
The original method on road surface runoff monitoring involves installation
of equipments onto the bridge deck or the parapets on both sides of the
expressway. After reviewing by relevant government departments, including the
Hong Kong Police Force and Fire Services Department, the installation of
equipment was considered causing disturbance to other road users including the
fire services and police vehicles during emergency operation and considered
relatively unsafe for the ET staff working on the expressway.
3.3
An alternative
proposal on the monitoring method using a water tanker to simulate an
artificial rainfall by spraying water onto the catchment area of the monitoring
gully during bridge closure at night was prepared. The alternative proposal was
approved by EPD. A procedural guide was also prepared. The guide was vetted by
the IEC and the Engineer and was reviewed by EPD.
3.4
Two periods of monitoring during the first 3 months and after
6 months of the opening of the
3.5
The commencement of the road surface runoff monitoring
programme was postponed to September 2007 due to the requirement in obtaining
consent and relevant permits and licenses from relevant government departments for
working on the bridge deck. The monitoring of road surface runoff from
carriageway was completed on 1 March 2008.
3.6
All samples were cooled to 4°C without being frozen and delivered to a HOKLAS laboratory
within 24 hours for analysis for the following pollutants in highway runoff:
Total suspended solids
Total organic carbon
Chemical oxygen demand
Nitrate and nitrite
Total Kjeldahl Nitrogen
Total phosphorus
Copper
Lead
Zinc
3.7 Water samples were collected from six different road gullies, three on each side of the carriageways. The exact monitoring locations were recorded in terms of nearby lighting pole / highways chainage.
3.8
The monitoring of road surface runoff from carriageway was
completed on 1 March 2008. No monitoring was carried out in the reporting
month.
4.1
As required under Clause 6.7, 6.9 and
6.10 of the Environmental Permit EP-162/2003/B, Clause 3.4 of the Environmental
Permit EP-290/2007 and Section 6.3.2 – 6.3.4 of the EM&A Manual,
operational disturbance on intertidal bird
communities, bridge lighting scheme and bird collisions, and replanted
mangroves have to be monitored bi-monthly (for 2 years), monthly (for 3 years)
and quarterly (for 2 years) respectively.
4.2
The trigger and
action levels for bird density for the monitoring on intertidal bird
communities are provided in Appendix B.
4.3
Equipment
used for monitoring included a 20x - 60x telescope, 10 x 42 binoculars, and a hand-held
GPS.
4.4
Two
monitoring locations were selected: Ngau Hom Shek (NHS) and Sheung Pak Nai
(SPN). The NHS site locates adjacent to
the
Intertidal Mudflat Monitoring
4.5
The
abundance and diversity of bird species within a
4.6
The
density and diversity of bird species were then compared with the baseline data
recorded from September 2001 to May 2002, as presented in the Shenzhen Western
Corridor EIA Report (EIA).
Tideline Monitoring
4.7
A
survey was conducted along a
Total
area of a transect =
4.8
Telescope
and binoculars were used to scan from one end to the other end of the transect.
A total of 1.5 minutes were spent in
each section. The number and species of
birds were recorded in each section. The
same method was used at the SPN site, except that there was no bridge alignment
and the transect was set on a random section along the tideline.
4.9
The density
of birds within the tideline transects at NHS and SPN were then tested for
their significance of difference using parametric t-test, or non-parametric
Mann-Whitney test, where:
Null
Hypothesis = No difference in bird densities along the tidelines at NHS and SPN
4.10
Additionally,
bird abundance and species composition were being compared with the baseline
data recorded from September 2001 to May 2002, as presented in the EIA.
Monitoring of Effects of Shade
4.11
In
order to monitor the effects of the shade of the HK-SWC to birds, the density
and composition of bird species were recorded on the mudflat underneath the HK-SWC
in 3 strips that lie parallel to it: 1) the strip of mudflat right under the
bridge (recommended by the EM&A Manual); 2) the strip of mudflat within the
shade; and 3) the strip of mudflat outside the shade and bridge. The strips extended from the shore towards the
sea. Monitoring was carried out during
low tide when at least
Total
area of a strip =
4.12
Since
the sun does not always shine right above the bridge, the shade of the bridge
rarely lies right under the bridge. It
is therefore recommended to follow the shade of the bridge and collect
information there, in addition to collecting information from right under the
bridge as recommended by the EM&A Manual.
4.13
The
collected information from the 3 strips of mudflat were being tested for their
significance of difference using the parametric t-test, or non-parametric
Mann-Whitney test, where:
Null
Hypothesis = No difference in bird densities on different strips of mudflat
4.14
The intertidal bird surveys were conducted on 21 May 2009. The weather was sunny. The temperature was 24.8 oC - 30.9oC
and the humidity was 73% - 94%.
Intertidal Mudflat Monitoring
4.15
Graph 4.1 shows the number and species of shorebirds recorded
at the
Graph 4.1 Abundance
and Species Composition of Shorebirds on the Exposed Mudflats (

4.16
At the NHS and SPN sites, only 1 species, Little Egret Egretta garzetta, was recorded during the survey. A
total of 3 and 4 individuals were recorded at NHS and SPN respectively. While abundance and species diversity were
approximately the same at both sites, there was no evidence to suggest any
adverse impacts from SWC operation on shorebird communities during the survey.
4.17
Table 4.1 compares the density and number of shorebird species
recorded during the EIA and the recent survey.
Table
4.1 Density and Number of Shorebird
Species Recorded during the Previous EIA and the Survey on 21 May 2009 on the Exposed
Mudflats (
|
|
Density of
Shorebirds (Birds/Ha) |
No. of species |
||
|
|
Ngau Hom Shek |
Sheung Pak Nai |
Ngau Hom Shek |
Sheung Pak Nai |
|
Current Survey |
3 |
4 |
1 |
1 |
|
Previous EIA |
2.3 |
4.2 |
1.3 |
1.8 |
4.18
The shorebird density and diversity at NHS recorded during
this survey were approximately the same as the numbers recorded during EIA. There was no evidence to suggest any adverse
impacts from SWC operation on shorebird communities during the survey.
4.19
The
abundance and diversity of shorebirds recorded at NHS during this survey (1
species of 3 individuals) were lower than the previous monitoring survey
conducted in March 2009 (4 species of 28 individuals). The decrease in abundance is possibly due to
the transition
from winter period (including March), when large amount of shorebirds aggregate
in Deep Bay, to summer period, where all the winter visitors are gone.
Tideline Monitoring
4.20
Graph 4.2 presents the abundance and species composition of
shorebirds recorded on the
Graph 4.2 Abundance
and Species Composition of Shorebirds along the Tidelines (

4.21
At
the NHS impact monitoring site, 2 species of 14 individuals of shorebirds (Great
Egret Egretta
alba,
and Little Egret Egretta garzetta) were recorded; whereas at the SPN control site, 3
species of 27 individuals of shorebirds (Little Egret Egretta garzetta, Great Egret Egretta alba and Green Sandpiper Tringa ochropus) were recorded.
4.22
The tideline transect at the NHS impact monitoring site recorded
approximately the same species diversity as, but lower abundance than, the SPN
control site. Although the SPN site
recorded higher abundance than the NHS site, nevertheless, a parametric t-test
found no statistically significant difference between the bird abundance along
the tidelines at NHS and SPN (P=0.148).
The result suggests that no adverse impact on shorebird communities was
observed during the operation of the HK-SWC during the survey.
4.23
Table 4.2 compares the density and number of shorebird species
recorded during the EIA and the recent survey.
Table 4.2 Density
and Number of Shorebird Species Recorded during the Previous EIA and the Survey
on 21 May 2009 along the Tidelines (
|
|
Density of
shorebird (birds/ha) |
No. of species |
||
|
|
Ngau Hom Shek |
Sheung Pak Nai |
Ngau Hom Shek |
Sheung Pak Nai |
|
Current survey |
28 |
54 |
2 |
3 |
|
Previous EIA |
23.2 |
58.2 |
1.8 |
2 |
4.24
During this survey, the shorebird
density and diversity at the NHS impact monitoring site and SPN control site
were approximately the same as that recorded during the previous EIA. The results of this
survey suggest that the operation of HK-SWC had no adverse effect on the shorebird communities
during this survey.
4.25
When compare the recent survey with the
previous survey conducted in March 2009, the density and species diversity of
shorebirds recorded during this survey (28 birds/ha of 2 species) were lower
than the previous survey (94 birds/ha of 2 species) at NHS. While for SPN, this survey also recorded
lower abundance than the previous survey in March (this survey – 54 birds/ha of
3 species; previous survey – 110 birds/ha of 5 species). The decrease in recorded bird abundance is
possibly due to the transition from winter period (including March), when large
amount of shorebirds aggregate in Deep Bay, to summer period, where all the
winter visitors are gone.
Monitoring of Effects of Shade
4.26
During the survey, only two sets of data, ‘Under Bridge’ and ‘On
Exposed Mudflat’, were collected, as the shade was right under the bridge.
4.27
Graph 4.3 presents the results recorded during the survey for
effects of shade on the strips of mudflat (
Graph 4.3 Abundance and Species Composition of
Shorebirds on the Strips of Mudflats (

dfddfd
4.28
At the strip of mudflat right under the HK-SWC (Under Bridge),
no shorebird was recorded during the monitoring survey; whereas 1 species (Little
Egret Egretta garzetta) of 2 individuals were recorded on the
exposed mudflat.
4.29
The recent monitoring survey showed that bird abundance and
diversity were not of significant difference between the strips of mudflat
“Under Bridge” and “On Exposed Mudflat”.
Moreover, a statistical Mann-Whitney Rank Sum test found no
statistically significant difference between the bird abundance within the two
strips of mudflat (P=0.690). This result suggests that the physical existence
of the HK-SWC and its shade has no adverse impact on the shorebird communities
at NHS during the recent survey.
4.30
As discussed in the operation monitoring report dated November
2007, distribution of shorebirds may be affected by a number of abiotic or
biotic factors apart from the operation of the HK-SWC, and they are listed
below:
l
Early-staged establishment of benthos communities in the
mudflat under bridge after the construction phase provide less food resource for
shorebirds, which may account for the lower number of shorebirds recorded under
the bridge. However, benthos communities
in mudflat under the bridge are expected to build up gradually in long-term and
such factor should be diminished in the future.
l
The curve-shaped tideline at some locations may provide less
feeding area and feeding opportunities for shorebirds, which may affect their
distribution at NHS.
l
The uneven and patchy distribution of shorebirds in nature
means that it may cause bias in statistical analysis.
l
A
succession of oyster farms was found located on the mudflat approximately
4.31
A
camera and a pair of binoculars were required during the monitoring process.
4.32
The
monitoring of bird collisions took place along the Hong Kong-Shenzhen Western Corridor
(HK-SWC), which is approximately
4.33
A
survey was conducted to assess the impacts of different lighting schemes on
bird mortality as caused by collision with the bridge and associated
structures. In order to monitor the bird’s
mortality, a survey was carried out along the HK-SWC at both sides of the
carriageway covering both the
4.34
The
four lighting schemes are listed as follows:
§ Scheme 1 –
Monday to Thursday and Sunday, 19.30-22.00. Architectural lighting for the tower.
§ Scheme 2 –
Friday, Saturday and general festival, 19.30-22.00. Architectural lighting for the tower and side
faces of the deck.
§ Scheme 3 – Special festival and
events, 19.30-22.00. Architectural lighting
for the tower, stay cables and the side faces of the deck.
§ Scheme 4 –
During inclement weather, turn off the architectural lighting.
4.35
The
survey was conducted on 26 May 2009 at 8 pm. Lighting Scheme 1 was being
monitored.
4.36
No dead
bird was found on the bridge nor floating on water surface during the survey. There was no significant evidence to suggest
adverse impacts from the HK-SWC on bird collision.
4.37
The
monitoring of the survival and growth of the compensatory mangrove plantation
took place right below the HK-SWC on the mudflat near the shore at NHS. The total area of the plantation was
4.38
Monitoring
of replanted mangrove was not carried out in the reporting month.
4.39
All of
the operation phase mangrove monitoring has been conducted.
.
5.1
As required under Clause 6.2 of the
Environmental Permit EP-162/2003/B, monitoring on the sedimentation rate in
5.2
The monitoring work took place every
month starting from the construction phase and up to one year after the project
has commenced the operation. Additional work may be needed subject to the
weather condition.
5.3
Monitoring was carried out at 7
monitoring stations as specified in the approved Sedimentation Rate Monitoring
Plan at Tsim Bei Tsui, Mai Po mudflat and those between HK-SWC and Tsim Bei
Tsui. These include two locations at Tsim Bei Tsui (Stations P1 & P2), three
locations at the Mai Po Mudflat (Stations P3 to P5) and two locations near Sha
Kiu Tsuen (Stations P6 & P7).
5.4
The sedimentation rate monitoring in
6.1
Site audits were
carried out on a weekly basis to monitor environmental issues on the site to confirm
that all mitigation measures were implemented properly. The summary of site
audit in the reporting period is attached in Appendix C.
6.2
All
permits/licences/notifications obtained as of the reporting period are
summarised in Table 6.1
Table 6.1 Summary of
Environmental Notification, Licensing and Permit Status
|
Permit No. |
Valid Period |
Description |
Status |
|
|
From |
To |
|||
|
Environmental
Permit |
||||
|
EP-162/2003/B |
19 Jan. 04 |
- |
1.
Construction
and operation of a 2.
Construction
and operation of a |
Valid |
|
EP-290/2007 |
20 Nov. 07 |
- |
1.
Operation
of a 2.0km dual 3-lane carriageway elevated structure of the |
Valid |
6.3
The ET conducted site inspections on 6, 14, 21 and 26 May 2009.
6.4
No specific
finding was identified in the reporting month.
Environmental Mitigation
Implementation Schedule (EMIS)
6.5
According to the Environmental Permit (EP-162/2003/B), the mitigation measures detailed
in the permits are required to be implemented. An updated summary of the EMIS
is presented in Appendix D.
6.6
No exceedance was recorded in
the reporting month.
6.7
The Event and Action Plans for feeding shorebirds are
presented in Appendix B.
6.8
Appendix E
presents the environmental complaint flow diagram of the Project.
6.9 No complaint, summon or prosecution related to environmental issues was received or made against the Project in the reporting period.
7.1
Key issues to be considered in the
coming month include:
·
Maintain sufficient cleaning works for the carriageway
by vacuum air sweeper(s) to remove grits and pollutants; and
·
Implementation of the Emergency Response Plan for
Spillage of Chemicals.
7.2
Tentative environmental monitoring and
audit schedule for the next reporting month is shown in Appendix F.
8.1
Environmental impact monitoring was
performed between 1 and 31 May 2009. All monitoring results in the reporting
period were checked and reviewed.
8.2
No operational noise monitoring was carried
out in the reporting month since the monitoring had been completed.
8.3
No road surface
runoff from carriageway monitoring was carried out in the reporting month since
the monitoring had been completed.
8.4
No bird mortality was recorded during this
month’s bridge lighting scheme and bird collisions survey.
8.5
From
the intertidal bird communities monitoring, the physical existence of the
HK-SWC and its shade did not show an adverse impact on the shorebird
communities at NHS.
8.6
No sedimentation
rate monitoring was carried out in the reporting month since the monitoring had
been completed.
8.7
No
specific observation was identified during the site audits in the reporting
month.
8.8
No complaint,
notification of summons or prosecution related to environmental issues was made
against the Project in the reporting period.
8.9
According to the environmental audits
performed, the following recommendations were made:
·
Maintain sufficient cleaning works for the carriageway
by vacuum air sweeper(s) to remove grits and pollutants.
·
Implement the Emergency Response Plan for Spillage of
Chemicals.