TABLE OF CONTENTS

 

Page

EXECUTIVE SUMMARY............................................................................................................................... I

Environmental Monitoring Works                                                                                                         I

Reporting Change                                                                                                                              I

Environmental Complaints and Prosecution                                                                                          I

Future Key Issues                                                                                                                             I

1.         INTRODUCTION.............................................................................................................................. 1

Background                                                                                                                                     1

Project Organization                                                                                                                         1

Summary of the EM&A Requirements                                                                                                1

2.         OPERATIONAL NOISE MONITORING............................................................................................... 2

Monitoring Requirements                                                                                                                   2

Monitoring Parameters, Frequency and Duration                                                                                 2

Monitoring Locations                                                                                                                         2

Results and Observations                                                                                                                  2

3.         WATER QUALITY........................................................................................................................... 3

Monitoring Requirements                                                                                                                   3

Monitoring Parameters, Frequency and Duration                                                                                 3

Monitoring Locations                                                                                                                         3

Results and Observations                                                                                                                  3

4.         ECOLOGY..................................................................................................................................... 4

Monitoring Requirements                                                                                                                   4

Operational Disturbance on Intertidal Bird Communities                                                                       4

Bridge Lighting Scheme and Bird Collisions                                                                                        9

Replanted Mangroves                                                                                                                        9

5.         SEDIMENTATION RATE MONITORING............................................................................................ 10

Monitoring Requirements                                                                                                                 10

Monitoring Parameters, Frequency and Duration                                                                                10

Monitoring Locations                                                                                                                       10

Results and Observations                                                                                                                10

6.         ENVIRONMENTAL AUDIT.............................................................................................................. 10

Site Environmental Audit                                                                                                                  10

Status of Environmental Licensing and Permitting                                                                              10

Implementation Status of Environmental Mitigation Measures                                                              11

Summary of Exceedances of Environmental Quality Performance Limit                                                11

Implementation Status of Environmental Complaint Handling Procedures                                              11

7.         FUTURE KEY ISSUES.................................................................................................................. 11

Key Issues for the Coming Month                                                                                                     11

Environmental Monitoring Programme for the Next Month                                                                   11

8.         CONCLUSIONS AND RECOMMENDATIONS................................................................................... 12

Conclusion                                                                                                                                     12

Recommendations                                                                                                                          12

EXECUTIVE SUMMARY

Environmental Monitoring Works

Reporting Change

Environmental Complaints and Prosecution

Future Key Issues

1.         INTRODUCTION

Background

Project Organization

Summary of the EM&A Requirements

2.         OPERATIONAL NOISE MONITORING

Monitoring Requirements

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Results and Observations

3.         WATER QUALITY

Monitoring Requirements

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Results and Observations

4.         ECOLOGY

Monitoring Requirements

Operational Disturbance on Intertidal Bird Communities

Bridge Lighting Scheme and Bird Collisions

Replanted Mangroves

5.         SEDIMENTATION RATE MONITORING

Monitoring Requirements

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Results and Observations

6.         ENVIRONMENTAL AUDIT

Site Environmental Audit

Status of Environmental Licensing and Permitting

Implementation Status of Environmental Mitigation Measures

Summary of Exceedances of Environmental Quality Performance Limit

Implementation Status of Environmental Complaint Handling Procedures

7.         FUTURE KEY ISSUES

Key Issues for the Coming Month

Environmental Monitoring Programme for the Next Month

8.         CONCLUSIONS AND RECOMMENDATIONS

Conclusion

Recommendations

 

 

 

 

 

 

 

List of Tables and Graphs

 

Table 2.1           The Noise Monitoring Locations.................................................................................... 2

Graph 4.1          Abundance and Species Composition of Shorebirds on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009.................................................... 5

Table 4.1           Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai    6

Graph 4.2          Abundance and Species Composition of Shorebirds along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009............................................................. 6

Table 4.2           Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai 7

Graph 4.3          Abundance and Species Composition of Shorebirds on the Strips of Mudflats (250 m x 40 m) “Under Bridge” and “On Exposed Mudflat” at Ngau Hom Shek – 21 May 2009......................................... 8

Table 6.1           Summary of Environmental Notification, Licensing and Permit Status............................. 10

Table 2.1           The Noise Monitoring Locations

Graph 4.1          Abundance and Species Composition of Shorebirds on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009

Table 4.1           Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai

Graph 4.2          Abundance and Species Composition of Shorebirds along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009

Table 4.2           Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai

Graph 4.3          Abundance and Species Composition of Shorebirds on the Strips of Mudflats (250 m x 40 m) “Under Bridge” and “On Exposed Mudflat” at Ngau Hom Shek – 21 May 2009

Table 6.1           Summary of Environmental Notification, Licensing and Permit Status

 

 

List of Figures

 

Figure 1.1         Project Organization

Figure 1.2         Layout of Work Site

Figure 4.1         Locations of the Monitoring Sites for Intertidal Bird Communities

 

 

List of Appendices

 

Appendix A        Contact of Key Environmental Personnel

Appendix B       Requirements, Event and Action Plans for the Ecological Monitoring during Operation Phase

Appendix C       Site Inspection Records

Appendix D       Summary of Environmental Mitigation Implementation Schedule

Appendix E       Complaint Flow Diagram and Complaint Log

Appendix F        Environmental Monitoring Schedules

 




EXECUTIVE SUMMARY

 

This is the twenty-third monthly Environmental Monitoring and Audit (EM&A) report prepared by ENSR Asia (HK) Ltd. (ENSR), which was integrated into AECOM Asia Company Limited as of 1 May 2009, the designated Environmental Team (ET), for the operational phase of the Project “Hong Kong-Shenzhen Western Corridor”. Operation of the Project commenced on 1 July 2007. This report presents the results of EM&A works conducted between 1 and 31 May 2009.

 

Weekly site audits, monitoring of intertidal bird communities and bridge lighting scheme and bird collisions were carried out in the reporting month. Environmental mitigation measures and environmental complaint handling procedures were also implemented.

Environmental Monitoring Works

Noise

No operational noise monitoring was carried out in the reporting month. The last operational noise monitoring was completed on 23 June 2008.

 

Water Quality

No road surface runoff monitoring was carried out in the reporting month. The last road surface runoff from carriageway monitoring was completed on 1 March 2008.

 

Ecology

The twelfth monitoring of operational disturbance on intertidal bird communities was carried out on 21 May 2009. During the survey, the physical existence of the HK-SWC and its shade did not show an adverse impact on the shorebird communities at NHS.

 

The twenty-third monthly bridge lighting scheme and bird collisions monitoring was conducted on 26 May 2009. No bird mortality was recorded in this monitoring.

 

Sedimentation Rate Monitoring

No sedimentation rate monitoring was carried out in the reporting month. The last sedimentation rate monitoring was completed on 17 June 2008.

 

Environmental Licensing and Permitting

Permits granted to the Project include the Environmental Permits for the Project (EP-162/2003/B and EP-290/2007).

 

Environmental Site Audit

Weekly environmental site audits were carried out in the reporting month. No specific observation was identified.

Reporting Change

There was no reporting change in this month.

Environmental Complaints and Prosecution

No complaint related to environmental issues was made against the Project in the reporting period. 

Future Key Issues

Key issues to be considered in the coming month include:

 

·         Maintain sufficient cleaning works for the carriageway by vacuum air sweeper(s) to remove grits and pollutants; and

·         Implement the Emergency Response Plan for Spillage of Chemicals.


1.       INTRODUCTION

Background

1.1               ENSR Asia (HK) Ltd. (ENSR) which was integrated into AECOM Asia Company Limited as of 1 May 2009, (hereinafter called the “ET”) was appointed by Highways Department (hereinafter called the “Client”) to undertake Environmental Monitoring and Audit for “Hong Kong-Shenzhen Western Corridor” (hereinafter called the “Project”) during operational phase. Under the requirements of Section 6 of Environmental Permit EP-162/2003/B and Section 3 of Environmental Permit EP-290/2007, EM&A programme as set out in the EM&A Manuals is required to be implemented. In accordance with the Environmental Permit and the EM&A Manuals, environmental monitoring of operational noise, water quality, ecology and sedimentation rate are required for the Project.

1.2               Operation for the Project commenced on 1 July 2007. This report summarises the environmental monitoring and audit works for the Project between 1 and 31 May 2009.

Project Organization

1.3               The structure of the environmental management team is shown in Figure 1.1. Contacts of key environmental staff of the Project are shown in Appendix A.

1.4               A layout plan of the Project is provided in Figure 1.2.

Summary of the EM&A Requirements

1.5               The EM&A programme requires environmental monitoring for operational noise, water quality, ecology and sedimentation rate. The EM&A requirements for each item are described in subsequent sections, including:

·         Monitoring parameters;

·         Environmental mitigation measures, as recommended in the project EIA final report;

·         Environmental requirements in the contract documents.

 

1.6               Site audits findings are described in Section 6.

1.7               Advice on the implementation status of environmental protection and pollution control/mitigation measures are summarised in Section 6 of the Report.

 

 


2.       OPERATIONAL NOISE MONITORING

Monitoring Requirements

2.1               Noise monitoring is required to monitor the operational noise level at the nearby sensitive receivers during peak traffic hour.

2.2               The measured noise level will be compared to the predicted traffic noise levels in the EIA under full provision of the mitigation measures.

Monitoring Parameters, Frequency and Duration

2.3               The traffic noise level should be measured twice within the first year of the road opening. Measurements should be made in terms of the A-weighted L10 over three 30-mins periods during the peak traffic hour. Other parameters L90 and Leq would be included for reference purpose.

Monitoring Locations

2.4               Noise monitoring was required to be carried out at NSRs SWC-AN1 and SWC-AN2. The monitoring locations are summarized in Table 2.1.

 

 Table 2.1     The Noise Monitoring Locations

 

Monitoring Station

Location

Monitoring Type

Description

SWC-AN1

Village House at Ngau Hom Shek

Façade

G/F

SWC-AN2

Village House at Ngau Hom Shek

Façade

G/F

Results and Observations

2.5               Operational noise monitoring was completed on 23 June 2008. No monitoring was carried out in the reporting month.

 

 

 


3.       WATER QUALITY

Monitoring Requirements

3.1               The monitoring is to determine the characteristics of bridge runoff in particular the first flush from the HK-SWC bridge during rain-storm events and to review the frequency of road cleaning.

3.2               The original method on road surface runoff monitoring involves installation of equipments onto the bridge deck or the parapets on both sides of the expressway. After reviewing by relevant government departments, including the Hong Kong Police Force and Fire Services Department, the installation of equipment was considered causing disturbance to other road users including the fire services and police vehicles during emergency operation and considered relatively unsafe for the ET staff working on the expressway.

3.3               An alternative proposal on the monitoring method using a water tanker to simulate an artificial rainfall by spraying water onto the catchment area of the monitoring gully during bridge closure at night was prepared. The alternative proposal was approved by EPD. A procedural guide was also prepared. The guide was vetted by the IEC and the Engineer and was reviewed by EPD.

Monitoring Parameters, Frequency and Duration

3.4               Two periods of monitoring during the first 3 months and after 6 months of the opening of the HK-SWC Bridge would be required. The monitoring should include in total 12 sampling / rainstorm events (12 sets of data) and cover the dry season period. A total of 6 sets of sampling data should be collected during the first 3 months after the opening of the HK-SWC bridge. The other 6 sets of sampling data should be collected in month 7 to month 9 after opening of the HK-SWC Bridge. The minimum interval between two sampling events shall not be less than 4 days.

3.5               The commencement of the road surface runoff monitoring programme was postponed to September 2007 due to the requirement in obtaining consent and relevant permits and licenses from relevant government departments for working on the bridge deck. The monitoring of road surface runoff from carriageway was completed on 1 March 2008.

3.6               All samples were cooled to 4°C without being frozen and delivered to a HOKLAS laboratory within 24 hours for analysis for the following pollutants in highway runoff:

ŸTotal suspended solids

ŸTotal organic carbon

ŸChemical oxygen demand

ŸNitrate and nitrite

ŸTotal Kjeldahl Nitrogen

ŸTotal phosphorus

ŸCopper

ŸLead

ŸZinc

Monitoring Locations

3.7               Water samples were collected from six different road gullies, three on each side of the carriageways. The exact monitoring locations were recorded in terms of nearby lighting pole / highways chainage.

Results and Observations

3.8               The monitoring of road surface runoff from carriageway was completed on 1 March 2008. No monitoring was carried out in the reporting month.

4.       ECOLOGY

Monitoring Requirements

4.1               As required under Clause 6.7, 6.9 and 6.10 of the Environmental Permit EP-162/2003/B, Clause 3.4 of the Environmental Permit EP-290/2007 and Section 6.3.2 – 6.3.4 of the EM&A Manual, operational disturbance on intertidal bird communities, bridge lighting scheme and bird collisions, and replanted mangroves have to be monitored bi-monthly (for 2 years), monthly (for 3 years) and quarterly (for 2 years) respectively.

4.2               The trigger and action levels for bird density for the monitoring on intertidal bird communities are provided in Appendix B.

Operational Disturbance on Intertidal Bird Communities

Monitoring Equipment

4.3               Equipment used for monitoring included a 20x - 60x telescope, 10 x 42 binoculars, and a hand-held GPS.

Monitoring Locations

4.4               Two monitoring locations were selected: Ngau Hom Shek (NHS) and Sheung Pak Nai (SPN).  The NHS site locates adjacent to the Hong Kong - Shenzhen Western Corridor (HK-SWC), and provides information for potential operational phase disturbance.  The SPN site was used as a control site during the monitoring process in construction phase.  In this Project, the SPN site was also used as a control site to maintain consistency.  It is located approximately 950 m to the southwest of NHS.

Monitoring Methodology

 

Intertidal Mudflat Monitoring

 

4.5               The abundance and diversity of bird species within a 100 m x 100 m quadrat (10,000 m2) of exposed mudflat were recorded.  The monitoring was carried out during low tide when at least 100 m of mudflat was exposed.  Data was recorded at both NHS and SPN sites.  

4.6               The density and diversity of bird species were then compared with the baseline data recorded from September 2001 to May 2002, as presented in the Shenzhen Western Corridor EIA Report (EIA).

 

Tideline Monitoring

 

4.7               A survey was conducted along a 10 m wide belt transect centred along the tideline at NHS and SPN.  The survey was conducted during low tide when at least 100 m of mudflat was exposed.  The transect at NHS extended 250 m from the alignment of the HK-SWC towards both sides (Figure 4.1).  The transect was divided into 10 sections of 50 m.

Total area of a transect = 10 m x 500 m = 5,000 m2

4.8               Telescope and binoculars were used to scan from one end to the other end of the transect.  A total of 1.5 minutes were spent in each section.  The number and species of birds were recorded in each section.  The same method was used at the SPN site, except that there was no bridge alignment and the transect was set on a random section along the tideline.

4.9               The density of birds within the tideline transects at NHS and SPN were then tested for their significance of difference using parametric t-test, or non-parametric Mann-Whitney test, where:

Null Hypothesis = No difference in bird densities along the tidelines at NHS and SPN

4.10           Additionally, bird abundance and species composition were being compared with the baseline data recorded from September 2001 to May 2002, as presented in the EIA.

 

Monitoring of Effects of Shade

 

4.11           In order to monitor the effects of the shade of the HK-SWC to birds, the density and composition of bird species were recorded on the mudflat underneath the HK-SWC in 3 strips that lie parallel to it: 1) the strip of mudflat right under the bridge (recommended by the EM&A Manual); 2) the strip of mudflat within the shade; and 3) the strip of mudflat outside the shade and bridge.  The strips extended from the shore towards the sea.  Monitoring was carried out during low tide when at least 250 m of mudflat was exposed.  Each strip was 250 m in length, 40 m in width (width of HK-SWC) and were divided into 5 sections of 50 m.

Total area of a strip = 250 m x 40 m = 10,000 m2

4.12           Since the sun does not always shine right above the bridge, the shade of the bridge rarely lies right under the bridge.  It is therefore recommended to follow the shade of the bridge and collect information there, in addition to collecting information from right under the bridge as recommended by the EM&A Manual.

4.13           The collected information from the 3 strips of mudflat were being tested for their significance of difference using the parametric t-test, or non-parametric Mann-Whitney test, where:

Null Hypothesis = No difference in bird densities on different strips of mudflat

Results and observation

4.14           The intertidal bird surveys were conducted on 21 May 2009.  The weather was sunny.  The temperature was 24.8 oC - 30.9oC and the humidity was 73% - 94%.

 

Intertidal Mudflat Monitoring

 

4.15           Graph 4.1 shows the number and species of shorebirds recorded at the 100 m x 100 m mudflat quadrats at NHS and SPN.

 

Graph 4.1      Abundance and Species Composition of Shorebirds on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009

 

4.16           At the NHS and SPN sites, only 1 species, Little Egret Egretta garzetta, was recorded during the survey.  A total of 3 and 4 individuals were recorded at NHS and SPN respectively.  While abundance and species diversity were approximately the same at both sites, there was no evidence to suggest any adverse impacts from SWC operation on shorebird communities during the survey.

4.17           Table 4.1 compares the density and number of shorebird species recorded during the EIA and the recent survey.

 

Table 4.1       Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 on the Exposed Mudflats (100 m x 100 m Quadrat) at Ngau Hom Shek and Sheung Pak Nai

 

 

Density of Shorebirds (Birds/Ha)

No. of species

 

Ngau Hom Shek

Sheung Pak Nai

Ngau Hom Shek

Sheung Pak Nai

Current Survey

3

4

1

1

Previous EIA

2.3

4.2

1.3

1.8

 

4.18           The shorebird density and diversity at NHS recorded during this survey were approximately the same as the numbers recorded during EIA.  There was no evidence to suggest any adverse impacts from SWC operation on shorebird communities during the survey.

4.19           The abundance and diversity of shorebirds recorded at NHS during this survey (1 species of 3 individuals) were lower than the previous monitoring survey conducted in March 2009 (4 species of 28 individuals).   The decrease in abundance is possibly due to the transition from winter period (including March), when large amount of shorebirds aggregate in Deep Bay, to summer period, where all the winter visitors are gone.

 

Tideline Monitoring

 

4.20           Graph 4.2 presents the abundance and species composition of shorebirds recorded on the 500 m x 10 m tideline transects at NHS and SPN.

 

Graph 4.2      Abundance and Species Composition of Shorebirds along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai – 21 May 2009

 

 

4.21           At the NHS impact monitoring site, 2 species of 14 individuals of shorebirds (Great Egret Egretta alba, and Little Egret Egretta garzetta) were recorded; whereas at the SPN control site, 3 species of 27 individuals of shorebirds (Little Egret Egretta garzetta,  Great Egret Egretta alba and Green Sandpiper Tringa ochropus) were recorded.

4.22           The tideline transect at the NHS impact monitoring site recorded approximately the same species diversity as, but lower abundance than, the SPN control site.  Although the SPN site recorded higher abundance than the NHS site, nevertheless, a parametric t-test found no statistically significant difference between the bird abundance along the tidelines at NHS and SPN (P=0.148).  The result suggests that no adverse impact on shorebird communities was observed during the operation of the HK-SWC during the survey.

4.23           Table 4.2 compares the density and number of shorebird species recorded during the EIA and the recent survey.

 

Table 4.2       Density and Number of Shorebird Species Recorded during the Previous EIA and the Survey on 21 May 2009 along the Tidelines (500 m x 10 m transect) at Ngau Hom Shek and Sheung Pak Nai

 

 

Density of shorebird (birds/ha)

No. of species

 

Ngau Hom Shek

Sheung Pak Nai

Ngau Hom Shek

Sheung Pak Nai

Current survey

28

54

2

3

Previous EIA

23.2

58.2

1.8

2

 

4.24           During this survey, the shorebird density and diversity at the NHS impact monitoring site and SPN control site were approximately the same as that recorded during the previous EIA.  The results of this survey suggest that the operation of HK-SWC had no adverse effect on the shorebird communities during this survey.

4.25           When compare the recent survey with the previous survey conducted in March 2009, the density and species diversity of shorebirds recorded during this survey (28 birds/ha of 2 species) were lower than the previous survey (94 birds/ha of 2 species) at NHS.  While for SPN, this survey also recorded lower abundance than the previous survey in March (this survey – 54 birds/ha of 3 species; previous survey – 110 birds/ha of 5 species).  The decrease in recorded bird abundance is possibly due to the transition from winter period (including March), when large amount of shorebirds aggregate in Deep Bay, to summer period, where all the winter visitors are gone.

 

Monitoring of Effects of Shade

 

4.26           During the survey, only two sets of data, ‘Under Bridge’ and ‘On Exposed Mudflat’, were collected, as the shade was right under the bridge.

4.27           Graph 4.3 presents the results recorded during the survey for effects of shade on the strips of mudflat (250 m x 40 m) at the NHS impact monitoring site.

 

 

 

 

 

 

 

 

 

 

 

Graph 4.3      Abundance and Species Composition of Shorebirds on the Strips of Mudflats (250 m x 40 m) “Under Bridge” and “On Exposed Mudflat” at Ngau Hom Shek – 21 May 2009

              

 

dfddfd

 
 


4.28           At the strip of mudflat right under the HK-SWC (Under Bridge), no shorebird was recorded during the monitoring survey; whereas 1 species (Little Egret Egretta garzetta) of 2 individuals were recorded on the exposed mudflat.

4.29           The recent monitoring survey showed that bird abundance and diversity were not of significant difference between the strips of mudflat “Under Bridge” and “On Exposed Mudflat”.  Moreover, a statistical Mann-Whitney Rank Sum test found no statistically significant difference between the bird abundance within the two strips of mudflat  (P=0.690).  This result suggests that the physical existence of the HK-SWC and its shade has no adverse impact on the shorebird communities at NHS during the recent survey.

4.30           As discussed in the operation monitoring report dated November 2007, distribution of shorebirds may be affected by a number of abiotic or biotic factors apart from the operation of the HK-SWC, and they are listed below:

l            Early-staged establishment of benthos communities in the mudflat under bridge after the construction phase provide less food resource for shorebirds, which may account for the lower number of shorebirds recorded under the bridge.  However, benthos communities in mudflat under the bridge are expected to build up gradually in long-term and such factor should be diminished in the future.

l            The curve-shaped tideline at some locations may provide less feeding area and feeding opportunities for shorebirds, which may affect their distribution at NHS.

l            The uneven and patchy distribution of shorebirds in nature means that it may cause bias in statistical analysis.

l            A succession of oyster farms was found located on the mudflat approximately 50 m away from both sides of the alignment of HK-SWC.  The oyster areas were observed to be a popular feeding ground for shorebirds and were frequently visited.  The abundant food resource in these areas may have a positive effect on the abundance and diversity of intertidal shorebirds on the strip of exposed mudflat at NHS.

 

 

Bridge Lighting Scheme and Bird Collisions

Monitoring Equipment

4.31           A camera and a pair of binoculars were required during the monitoring process.

Monitoring Locations

4.32           The monitoring of bird collisions took place along the Hong Kong-Shenzhen Western Corridor (HK-SWC), which is approximately 5.5 km long and 40 m wide.

Monitoring Methodology

4.33           A survey was conducted to assess the impacts of different lighting schemes on bird mortality as caused by collision with the bridge and associated structures.  In order to monitor the bird’s mortality, a survey was carried out along the HK-SWC at both sides of the carriageway covering both the Hong Kong and Shenzhen sections.  Attention was paid to the road surface while attempts were made to spot dead birds.  Sea surface was also scanned for any floating dead birds.

4.34           The four lighting schemes are listed as follows:

 

§      Scheme 1 – Monday to Thursday and Sunday, 19.30-22.00.  Architectural lighting for the tower.

§       Scheme 2 – Friday, Saturday and general festival, 19.30-22.00.  Architectural lighting for the tower and side faces of the deck.

§       Scheme 3 – Special festival and events, 19.30-22.00.  Architectural lighting for the tower, stay cables and the side faces of the deck.

§       Scheme 4 – During inclement weather, turn off the architectural lighting.

 

Results and observation

4.35           The survey was conducted on 26 May 2009 at 8 pm.  Lighting Scheme 1 was being monitored.

4.36           No dead bird was found on the bridge nor floating on water surface during the survey.  There was no significant evidence to suggest adverse impacts from the HK-SWC on bird collision.

Replanted Mangroves

Monitoring Locations

4.37           The monitoring of the survival and growth of the compensatory mangrove plantation took place right below the HK-SWC on the mudflat near the shore at NHS.  The total area of the plantation was 2,010.9 m2.  It was composed of 7,736 Kandelia obovata droppers.

Results and observation

4.38            Monitoring of replanted mangrove was not carried out in the reporting month.

4.39            All of the operation phase mangrove monitoring has been conducted.

.


5.       SEDIMENTATION RATE MONITORING

Monitoring Requirements

5.1               As required under Clause 6.2 of the Environmental Permit EP-162/2003/B, monitoring on the sedimentation rate in Deep Bay would be required on a monthly basis.

Monitoring Parameters, Frequency and Duration

5.2               The monitoring work took place every month starting from the construction phase and up to one year after the project has commenced the operation. Additional work may be needed subject to the weather condition.

Monitoring Locations

5.3               Monitoring was carried out at 7 monitoring stations as specified in the approved Sedimentation Rate Monitoring Plan at Tsim Bei Tsui, Mai Po mudflat and those between HK-SWC and Tsim Bei Tsui. These include two locations at Tsim Bei Tsui (Stations P1 & P2), three locations at the Mai Po Mudflat (Stations P3 to P5) and two locations near Sha Kiu Tsuen (Stations P6 & P7).

Results and Observations

5.4               The sedimentation rate monitoring in Deep Bay was completed on 17 June 2008. No monitoring was carried out in the reporting month.

 

 

6.       ENVIRONMENTAL AUDIT

Site Environmental Audit

6.1               Site audits were carried out on a weekly basis to monitor environmental issues on the site to confirm that all mitigation measures were implemented properly. The summary of site audit in the reporting period is attached in Appendix C.

Status of Environmental Licensing and Permitting

6.2               All permits/licences/notifications obtained as of the reporting period are summarised in Table 6.1

 

Table 6.1  Summary of Environmental Notification, Licensing and Permit Status

 

Permit No.

Valid Period

Description

Status

From

To

Environmental Permit

EP-162/2003/B

19 Jan. 04

-

1.        Construction and operation of a 3.2 km dual 3-lane carriageway elevated structure of the Shenzhen Western Corridor spanning across Deep Bay from Ngau Hom Shek to the section of the Shenzhen Western Corridor within the boundary within the Mainland.

2.        Construction and operation of a 340 m dual 3-lane carriageway of the Deep Bay Link connecting to the Shenzhen Western Corridor at Ngau Hom Shek.

Valid

EP-290/2007

20 Nov. 07

-

1.        Operation of a 2.0km dual 3-lane carriageway elevated structure of the Shenzhen Bay Bridge spanning across Deep Bay from Shenzhen Bay Bridge – Hong Kong Section to Shenzhen Bay Port, Hong Kong Port Area at Dongjiaotou.

Valid

Implementation Status of Environmental Mitigation Measures

6.3               The ET conducted site inspections on 6, 14, 21 and 26 May 2009.

6.4               No specific finding was identified in the reporting month.

Environmental Mitigation Implementation Schedule (EMIS)

6.5               According to the Environmental Permit (EP-162/2003/B), the mitigation measures detailed in the permits are required to be implemented. An updated summary of the EMIS is presented in Appendix D.

Summary of Exceedances of Environmental Quality Performance Limit

6.6               No exceedance was recorded in the reporting month.

6.7               The Event and Action Plans for feeding shorebirds are presented in Appendix B.

Implementation Status of Environmental Complaint Handling Procedures

6.8               Appendix E presents the environmental complaint flow diagram of the Project.

6.9               No complaint, summon or prosecution related to environmental issues was received or made against the Project in the reporting period.

 

 

7.                  FUTURE KEY ISSUES

Key Issues for the Coming Month

7.1               Key issues to be considered in the coming month include:

·         Maintain sufficient cleaning works for the carriageway by vacuum air sweeper(s) to remove grits and pollutants; and

·         Implementation of the Emergency Response Plan for Spillage of Chemicals.

 

Environmental Monitoring Programme for the Next Month

7.2               Tentative environmental monitoring and audit schedule for the next reporting month is shown in Appendix F.

 

 

8.       CONCLUSIONS AND RECOMMENDATIONS

Conclusion

8.1               Environmental impact monitoring was performed between 1 and 31 May 2009. All monitoring results in the reporting period were checked and reviewed.

8.2               No operational noise monitoring was carried out in the reporting month since the monitoring had been completed.

8.3               No road surface runoff from carriageway monitoring was carried out in the reporting month since the monitoring had been completed.

8.4               No bird mortality was recorded during this month’s bridge lighting scheme and bird collisions survey.

8.5               From the intertidal bird communities monitoring, the physical existence of the HK-SWC and its shade did not show an adverse impact on the shorebird communities at NHS.

8.6               No sedimentation rate monitoring was carried out in the reporting month since the monitoring had been completed.

8.7               No specific observation was identified during the site audits in the reporting month.

8.8               No complaint, notification of summons or prosecution related to environmental issues was made against the Project in the reporting period. 

Recommendations

8.9               According to the environmental audits performed, the following recommendations were made:

Water Quality Impact

·         Maintain sufficient cleaning works for the carriageway by vacuum air sweeper(s) to remove grits and pollutants.

·         Implement the Emergency Response Plan for Spillage of Chemicals.